Rain pushes back I-35W, I-94 closures
MINNEAPOLIS (KMSP) - Monday's rain has delayed construction and pushed back scheduled closures on Interstate 35W.
The Minnesota Department of Transportation says cews were unable to finish decking the 26th Street bridge over northbound I-35W on Monday night due to storms. To finish the project, northbound I-35W will be closed completely between Interstate 94 and Highway 62 from 10 p.m. Tuesday to 5 a.m. Wednesday.
As a result, other closures have been pushed back as well. Southbound I-35W will be closed completely between I-94 and Hwy. 62 from 10 p.m. Wednesday to 5 a.m. Thursday.
I-94 will be closed in both directions from 10 p.m. Thursday to 5 a.m. Friday.